Shoring a Load-Bearing Wall Removal: What the Plan Must Cover
Temporary shoring carries the floors and roof while a bearing wall is out. See what the shoring plan must cover in Ontario and what to ask before work starts.
Temporary shoring is a stand-in structure that carries the floors and roof above a load-bearing wall while the wall is cut out and the new beam goes in. In Ontario, a sound shoring plan names what is being carried, where the shores land, how they are braced, the order of work and when each one comes out.
This guide covers what that plan has to include and how to check it before work starts. If you are not yet sure the wall is structural, start with how to tell if wall is load bearing in our checks guide. If you are planning an opening, our load-bearing wall removal team builds the shoring, takes out the wall and sets the beam to the engineer’s drawings. For a wider look at the whole job, see our guide to load-bearing wall removal scope.
What does temporary shoring actually do?
Shoring moves the weight of whatever the wall carries onto a temporary frame, so the wall can come out without the floor above sagging or the roof settling. A bearing wall carries real load from floors, partitions, furnishings and, at the top of the house, the roof and snow.
A typical setup has three parts: a load-spreading member (a doubled beam or strongback) that touches the ceiling or joists, vertical posts that carry it down, and solid bearing under the posts. If any one of those three is weak, the system is weak.
Shoring is not the permanent fix. Our structural beam installation work replaces it with an engineered beam and posts, and the temporary frame is only there until that beam is carrying the load.
Who designs the shoring?
The engineer who sizes the new beam should also say how the load is held while the wall is out, or at least review the contractor’s method. The permanent beam, posts and footings are stamped drawings. The temporary support is often left to “the contractor will handle it”, and that is the gap to close.
It helps to know what the permit office asks for. Kitchener’s guide to removing a load-bearing wall lists scaled plan views of the floor where the wall is removed and of every floor above and below, showing joist directions, new beam sizes and supports, and the distance from the new beam to the next wall or beam on each side. It also requires an engineer’s stamped report or engineered software output for an LVL beam. The Township of Mapleton’s guide for building permit applications asks for the same plan views, with a designer’s stamp on the drawings.
Neither guide says anything about temporary support. That is normal: permit drawings describe the finished structure. The shoring plan is something you ask for, from the engineer or from the contractor, before the work date is booked. Our overview of when a framing project needs an engineer explains where an engineer’s stamp is expected.
What does Ontario’s regulation say about temporary support?

The Construction Projects regulation, O. Reg. 213/91, sets a clear principle for temporary support in its rules on formwork, falsework and re-shoring. Section 87 says these systems must be designed, constructed, supported and braced so that they can withstand all loads and forces likely to be applied to them, and section 91 requires sound and rigid footings capable of carrying the maximum load without settlement or deformation of the soil or structure below.
Those sections are written with concrete work in mind, so whether they apply to a given house depends on the project and who the constructor is. We treat them as the standard to design to anyway, because they describe how shoring fails: loads that were guessed, bracing that was skipped and bearing that was not checked.
What must the shoring plan cover?
A usable plan answers seven questions. The table is a checklist to hold up against any plan you are handed.
| Item | What the plan should say |
|---|---|
| Load being carried | Which floors, walls and roof land on this wall, and which way the joists run |
| Shore locations | Where posts and strongbacks go on each side of the wall, with room left to work |
| Bearing below | What each post sits on: slab, footing, beam or blocking, and whether it can take the load |
| Load spreading | Doubled beam, plates or planks that spread the load into the joists above and the floor below |
| Bracing | How posts are held from kicking out, and how the frame is tied to the ceiling and floor |
| Sequence | Order of install, cut, beam set, load transfer and removal, and who signs off each step |
| Monitoring | What is checked for movement, how often, and what happens if something shifts |
How do you know what the wall is carrying?
You trace the load from the roof down. On a two-storey house, a main-floor wall can be carrying the second-floor joists, the walls on the second floor and part of the roof. A wall in the middle of the house, running across the joists, usually carries the most. Your engineer’s plan views of the floors above and below show this, and so does opening the ceiling to look.
That load picture sets everything else. A wall that carries only a floor needs a lighter temporary frame than one that also carries a loaded wall above it. Skipping this step is how a shoring system ends up sized for the wrong job.
Where do the shores land?

Every post sends its load somewhere, and the surface under it has to take that load. In a basement, that may be the slab, a footing or an existing beam. On an upper floor, posts need to land over something that carries down to the foundation, not on an unsupported stretch of subfloor between joists.
A common weakness is a strong frame resting on a weak floor. If a shore lands on a floor system, the plan should say how that floor is stiffened, usually with blocking or a second set of posts below. If the point load will end up on a footing never designed for it, the engineer needs to hear about it now, not at beam day.
How is the frame braced and spread?
Posts alone are not a system. A doubled beam or strongback at the top spreads the load across several joists instead of crushing one. Plates or planks under the posts spread the load into the floor. Bracing, either diagonals or ties to the structure, keeps the posts from kicking out sideways if someone bumps them or the load shifts.
Shores go up on both sides of the wall, with enough clearance to work between them and the wall being removed. They are adjusted snug, taking up the load without lifting the structure. Overtightening can crack plaster and drywall as surely as under-supporting it.
What is the sequence of work?
The order of work protects the house. A sound sequence looks like this:
- Confirm the permit is issued and the engineer's drawings are on site.
- Strip finishes and relocate any services in the wall with the trades involved.
- Install the shoring on both sides and check bearing, bracing and snugness.
- Open the wall in stages and watch for movement.
- Remove the studs and plates, and prepare the bearing points for the beam.
- Set the beam and posts, fasten them to the engineer's schedule and confirm bearing.
- Release the shoring gradually, watching the new beam take the load.
- Book the inspection before anything is covered.
The shoring stays until the beam is fully carrying the load. It should never be treated as a permanent post, because it is not rated or built for long-term loading.
What do you check while the work is happening?

Movement is the signal. Hairline cracks at ceiling corners, doors that stick upstairs and a slight dip in a joist line are early signs that the load has shifted. A good crew watches for them at each step and stops to adjust before going further. Ask whether anyone is assigned to watch the floor above while the wall is open.
Where the project is large or the wall is carrying a lot, the engineer may want to visit during the work. Our guide on framing permits and inspections in Ontario explains which inspections the municipality expects before framing is covered.
What does the shoring change about cost and schedule?
Shoring adds time before the wall comes out and after the beam goes in, and it adds labour for building, adjusting and removing the frame. The drivers are the number of floors carried, the span of the opening, what the posts land on, how much of the house has to be protected and whether the engineer asks for site visits.
We do not give a number from a phone call, because the load and the bearing change the answer. We give a written scope after we have seen the wall, the floor above and the floor below. If you are comparing quotes, check that each one says what the shoring includes, because it is easy for one to leave it out.
What should you have ready before calling a framer?
- The stamped drawings for the beam and posts, or the name of the engineer doing them.
- Photos of the wall, the ceiling and the floor below, including any basement beams or posts.
- The direction of the floor joists above the wall, if you know it.
- A note of what is in the wall: ducts, plumbing stacks, wiring or a panel.
- The permit status and the inspection hold points listed on the permit.
- Your timeline, including any date the room has to be usable again.
With that in hand, a contractor can tell you in one visit what the shoring involves. Our pages on renovation framing and structural repair framing cover related structural work, and our framing contractor page explains how a project is scoped from the first visit.
Planning an opening and want the shoring spelled out before you commit? Tell us about it on our load-bearing wall removal page.
For the Mississauga permit and drawings that go with this work, see load-bearing wall removal in Mississauga.
Frequently asked questions

Do I need a shoring plan to remove a load-bearing wall in Ontario?
You need a plan for how the load is carried while the wall is out, whether or not the permit office asks to see it. The municipal guides we checked ask for drawings of the permanent beam and posts, so ask your engineer or contractor to put the temporary support in writing as well.
How long does temporary shoring stay in place?
Until the new beam is fully seated, fastened and carrying the load through its posts to solid bearing. The engineer's sequence decides when each shore comes out, and none should be released early.
Can adjustable steel posts alone hold up the floor above?
Not safely on their own. Posts need a load-spreading member above them, solid bearing below them and bracing so they cannot kick out. The floor or footing underneath has to be able to take the load, which is why the plan looks below the work as well as above it.
Will shoring damage my floors or ceilings?
Good shoring protects them. Plates spread the load, posts are raised only enough to take the weight, and the work is watched for movement. Hairline drywall cracks can still appear when the load changes hands, which is why finish work waits until the beam is in.
Who is responsible for the shoring on my project?
The engineer sizes the permanent beam and posts and should specify or approve the temporary support. The contractor builds it, watches it and removes it in the agreed order. Ask for that split in writing before the quote is signed.